Latest progress of Pakistan Project
After four months’ hard work, the commissioning stage of Pakistan project is nearing completion, the equipments we provided for them are one set of 20T rectangular regenerative melting furnace and two sets of 10T round tilting holding furnace. The whole set of furnaces were delivered in August 2015, our engineers went to Pakistan for furnace building in November 2015, the installation of furnaces have been completed in two months. Present stage is the commissioning of whole CCR line. In the below picture, our engineers are carefully discussing with local technicians in order to ensure the whole production line runs smoothly.